Based on FMC1278R3 and CS.00054:2018 Production Representative Hardware and Software should be used

Based on FMC1278R3 and CS.00054:2018 Production Representative Hardware and Software should be used for all verification testing unless approved differently by OEM via EMC Test Plan. 

The Production Representative Test Sample is built using production representative hardware and software constructed using production representative processes, tooling, etc.

Following Software Changes in addition to PCB Changes re-validation for test methods like ESD, CISPR 25 RE, BCI, RI ALSE , Hand Portable Transmitters, Transients, Voltage Dips and Dropouts may be required. 

FMC require DV testing to be performed using production representative components but not necessarily components constructed from production tooling.

EMC DV1 Testing for PCM (Powertrain Control Module) is normally performed with test software mutually agreed to by FMC D&R, EMC and the supplier.
EMC DV2 Testing for PCM must be completed using Production Intent Hardware and the latest available Application Software.

FCA require DUT Validation Testing done on Production Intent Samples using Production Intent Hardware and Software.
Production Intent Components must be used for the inputs and loads including switches, sensors, pulse width modulated loads, solenoids and motors.